From Run-Down House to a Dream Home in Mallorca: Getting Hands-On, Delays and the First Cost Overview

Chapter 13: Getting Hands-On and Taking a First Look at the Actual Project Costs


Dave begins a very special week in Mallorca. It is 11 October 2026, and for the first time he has to take care of practically everything himself: both the work on the construction site and the filming and production of the videos. His cameraman and one of his editors are on holiday. This means Dave has to return to the days when he personally took care of every detail.

There is still plenty to do inside the house. Although significant progress has been made over the past few weeks, the dry construction work has not yet been completed in every room. The bedroom, guest room, dressing room and ground floor still require further work.

That is why Dave wants to use this week to get involved in the interior work himself. He wants to complete as much as possible with his own hands while also showing how the construction project is progressing from a much more personal perspective.

[VIDEO LINK EPISODE 13 HERE]

Insulating and Boarding the Interior Walls


The First Work in the Guest Room

The first goal is to complete the guest room. Most of the supporting framework is already prepared. Only one wall still needs to be insulated before the boarding can begin.

Five-centimetre-thick mineral wool is placed between the profiles. Once the remaining section has also been insulated, Dave can start installing the OSB boards.

The boards are supplied in standard sizes and have to be measured individually and cut using a plunge saw. To ensure that the joints fit correctly, Dave has to pay attention to the alignment of each individual element. The boards have a tongue-and-groove system that allows them to fit neatly together.

They are then pre-drilled and secured with screws.

For Dave, fitting the first board to the wall is a small milestone. With every additional board, the initially lightweight and slightly flexible framework becomes a considerably more stable and solid wall.

During the work, he has to pay particular attention to the joints to ensure that no gaps remain. The cut-outs in special areas, for example around the roof beams, also have to be carefully adapted. Although Dave admits that he still has little experience with this kind of work, he is gradually finding his own working rhythm.

Learning as You Work

One of the first things Dave realises during these days is how much time can be spent simply looking for the right tool, preparing the materials or discovering that something has been forgotten.

Measuring, cutting, checking the alignment of the boards and keeping all the necessary tools within reach – all of this is part of a continuous learning process.

Once Dave organises his work more efficiently, he makes considerably faster progress. For him, one of the best aspects of this week is finally being able to work on the construction site himself.

His goal is to finish the guest room and then continue with the remaining walls. There is also a particular challenge waiting for him in the stairwell: this is where the ceiling is at its highest, making the work considerably more complicated.

An Important Decision: Gypsum Plasterboard or Clay Boards?


Two Materials with Different Properties

While Dave is working on the interior boarding, he faces a decision that could have a significant influence on the finished house: should he use conventional gypsum plasterboard or choose a more natural solution with clay boards and clay plaster?

The conventional option would be to cover the walls with gypsum plasterboard. This system is widely used, can be installed relatively quickly and is part of everyday work for many dry construction specialists in Mallorca.

However, Dave has received advice about an alternative with different properties: using clay plaster carrier boards followed by a layer of clay plaster.

To better understand the differences, he looks at four key aspects: indoor climate, the feel of the rooms, installation and costs.

The Impact on Indoor Climate

One of the most important differences lies in the ability to regulate humidity.

Gypsum plasterboard absorbs very little moisture and stores hardly any heat. Clay behaves differently: it can absorb considerably more moisture from the air and release it again later.

According to the explanations Dave receives, the walls of a normal room can buffer approximately two and a half litres of water when clay is used. With gypsum plasterboard, this capacity is less than one litre.

This can make a difference in everyday situations, for example after showering, while cooking or at night when people spend many hours in an enclosed room.

Clay also has a greater capacity to store heat. This is particularly interesting to Dave because the house is being insulated from the inside. Due to the mass of the material, heat from outside can enter the rooms more slowly. As a result, the air conditioning might also need to switch on less frequently.

Room Atmosphere, Appearance and Maintenance

Gypsum plasterboard allows for smooth and even surfaces. It can be used to create modern design solutions, sharp edges, shadow gaps and flush-mounted installations.

Clay, on the other hand, creates a different atmosphere. Its surface looks more matt, warmer and more natural. The mass of the material can also help reduce reverberation time inside the rooms.

There are also differences when it comes to maintenance. Clay surfaces are softer and their edges require appropriate protection. However, small areas of damage can be repaired relatively easily with a damp sponge.

Installation Time and Price Differences

When it comes to installation, gypsum plasterboard has a clear advantage: the system is quick to install and familiar to many professionals. The boards are fitted and screwed into place, the joints are filled and sanded, and the surfaces are then painted.

The clay solution requires considerably more manual work. The boards are heavy, need to be properly secured and subsequently receive a reinforcing layer with mesh. The clay plaster is then applied. The required drying times must be observed between the individual stages. This can extend the installation process by several days or even weeks.

In addition, specialists with experience in this type of finish are needed. This is particularly important if more elaborate design details are desired.

There is also a considerable difference in cost. According to the figures mentioned in the video, a finished gypsum plasterboard solution, including filling and painting, costs approximately €25–40 per square metre. The alternative with clay boards, reinforcement and clay plaster can cost between €80 and €130 per square metre.

Transporting the material to Mallorca adds further costs. For approximately 100 square metres of wall surface, Dave estimates the additional expense at around €5,000–9,000. A longer construction period must also be expected.

The decision is not an easy one. Dave places great importance on natural materials and a pleasant indoor climate, but at the same time he is aware that this solution represents a considerable additional investment.

The Installations Are Becoming an Increasing Problem


Delays Affecting the Entire Construction Site

While Dave is making progress inside the house, one area of the construction site is not moving forward as planned: the installations.

The responsible team is working on various systems throughout the house. These include fresh water, wastewater, electricity, network cabling and air conditioning.

Dave emphasises that the personal relationship with the specialists is good and that both sides understand each other’s difficulties. The problem is not communication, but the fact that not enough working hours are being spent on the construction site.

The original agreement was to complete the installations by 15 September. Two additional weeks were then allowed, meaning that the work should have been finished by the beginning of October. However, the actual progress is still insufficient.

The specialists have several projects running simultaneously and have to travel every day from a location approximately one hour away. As a result, they cannot spend the necessary amount of time on Dave’s construction site.

What Has Already Been Completed and What Is Still Missing

At this point, the electrical conduits have already been installed. The fresh water pipes also reach the technical room and some connection points inside the house, including the kitchen.

However, important work is still outstanding. The wastewater pipes have not yet been installed, and there has been very little progress with the air conditioning either. The various systems in the technical room still need to be connected and organised, including pumps and filters.

The problem is that the remaining construction work depends directly on these installations.

Dave could actually start working on the floor build-up already. However, the wastewater pipes have to be installed first. Without this step, the work cannot proceed properly.

The tiler is also affected by the delay. He can only start once the floor build-up has been completed and has had sufficient time to dry. In addition, some of the remaining interior walls can only be built after the floor build-up is finished.

As a result, the construction site is increasingly reaching a dead end: one outstanding task is preventing several subsequent trades from starting their work.

Completing the Rooms and Making the Interior Insulation Airtight


Working on the Window Reveals

Before the walls can be completely closed, Dave also has to finish the window reveals.

These areas between the windows and the walls require special preparation. Pieces of OSB are used for this purpose, and the surfaces are prepared so that an airtight connection to the rest of the construction can later be achieved.

The aim is to avoid thermal bridges and ensure that the internal insulation works properly.

Dave realises that this work is considerably more time-consuming than it initially appears. Every individual piece has to be measured and cut to size. The window reveals in just one room take approximately half a working day to complete.

Because he does not want to start all over again the following day, he decides to finish the window reveals in the master bedroom and dressing room as well.

Why Every Joint Must Be Carefully Sealed

Once the boards and window reveals have been prepared, the next step is to seal the transitions using a special sealing tape.

This tape is essential to prevent air from flowing through the joints and penetrating the internal insulation layer. That is why Dave emphasises that not a single section should be left open.

The team had previously run out of this material. It could not be found at the usual suppliers in Mallorca, so the new order from Würth had to come from Germany.

Once the tape finally becomes available, Dave can continue working. He looks at how the specialists have sealed the sections that have already been boarded and follows the same approach for all joints and any potential points where air could enter.

By the end, the guest room and dressing room have largely been boarded and sealed. The work on the window reveals in the master bedroom has also been completed. The hallway initially remains unfinished because the considerable height requires suitable scaffolding.

A New Outdoor Structure: The Pergola by the Garden


While Dave is working inside, another construction phase begins outside.

Preparations were already made during the structural work to build a pergola that connects directly to the house and faces towards the garden.

The structure will be made of wood. The first elements are prepared and treated before the crossbeams for the roof are gradually put into place.

However, the pergola will only cover part of the house. Specifically, it will extend across the area in front of the two windows belonging to the dining room and kitchen.

Its size is limited by the approved building area. As Dave explains, the permitted building area specified in the planning application has already been fully used.

He does mention that there may be other possibilities for the second half of the area, such as a very lightweight structure with climbing plants. However, he makes it clear that he does not want to experiment with anything that could cause legal difficulties later on.

His goal remains to build a house that fully complies with the approved plans and can be officially signed off without any problems. This certainty is more important to him than extending the structure in other ways.

Finding a Solution to Get the Installations Moving Again


An Agreement to Make Up for Lost Time

Towards the end of the week, Dave sits down again with Lawrence, the person responsible for the installation team.

The conversation leads to a practical solution. Both acknowledge that the situation is difficult and that the specialists currently have too many projects overlapping at the same time.

To prevent the construction site from falling even further behind schedule, they agree on a different arrangement for the coming days: Lawrence will temporarily stay in the mobile home where Dave’s team is currently living. Together, they will work on the installations.

Dave commits to supporting him with the work and preparing everything necessary to help move the water, wastewater and other pipe installations forward.

In addition, some of the workers responsible for the pergola have now returned to the construction site, meaning that this work can also continue.

This solution brings back some optimism. If they manage to complete the wastewater pipes during the following week, work on the floor build-up can begin afterwards. That would also make the next construction phases possible again.

The First Cost Overview: How Much Is the House Really Going to Cost?


The Purchase Price and the First Expenses

One of the most interesting moments in this episode is the first interim financial overview of the project.

Dave shows some of the information he has collected in an Excel spreadsheet, where he documents the costs of the entire construction project.

The purchase of the house and the land, including all associated expenses, initially came to a total of €56,776. This also includes notary and legal fees, as well as expenses related to the property search and the transaction.

However, Dave explains that he does not want to publish every individual item on his list. He does not believe it would be fair to disclose all the amounts associated with the various specialists and companies involved in the project.

From One Million Euros to an Estimated €1.6 Million

The original plan was for the entire project to cost approximately one million euros: around €500,000 for the purchase and another €500,000 for the renovation.

However, the project changed considerably. What had originally been planned as a renovation eventually became a new build, or rather a complete reconstruction. As a result, the costs increased significantly.

The first overall estimate later reached approximately €1.5 million. Dave now admits that even this amount will be exceeded.

The cost categories he mentions include:

  • Architecture and construction management.

  • Interior design and technical planning.

  • Structural construction and outdoor areas.

  • Swimming pool and pool technology.

  • Windows and window installation.

  • Dry construction and dry construction materials.

  • Sliding doors and track systems.

  • Painting work and clay plaster.

  • Tiling and sanitary installations.

  • Electrical installations and hot water.

  • Photovoltaic system.

  • Plants and garden work.

According to the figures shown in the video, planning services, architecture, construction management and other related professional services alone amount to approximately €9,093.

After roughly adding together the various items, Dave expects the final costs could reach approximately €1.6 million.

A Huge Investment and a Conscious Decision

Dave makes no secret of the fact that this is an exceptionally large amount and that the financial situation creates considerable pressure.

At the same time, he explains that he has consciously chosen high-quality materials and solutions for many aspects of the project. His intention is to build only once and do it properly. In doing so, he takes into account the specific requirements of the house and the features he wants to incorporate.

He does not hide the fact that the original budget has long been exceeded and that this investment represents a significant financial risk.

Nevertheless, he still gets a great deal of enjoyment from the project. A major part of his satisfaction comes from being involved in projects himself, making decisions and watching ideas gradually become reality.

The Real Goal: Enjoying the House Once It Is Finished


More Than Just Completing the House

At the end of the episode, Dave reflects on something that goes beyond the budget and the progress of the construction work.

With previous projects, he has often found that some of his enthusiasm faded once the work was finished. He loves putting things into practice, making changes and taking on new challenges. However, enjoying the finished result does not always come as naturally to him as the process of getting there.

With this house, he hopes things will be different.

He wants to relax there, spend time by the pool and actually enjoy using the house – for many years to come. Even the idea of one day sharing it with a family of his own is part of his hopes.

He does not yet know whether he will ultimately manage to switch off from construction work and fully enjoy the finished result. But he knows that this is one of his most important goals.

He also thanks everyone who follows his videos and has made it possible for him to realise projects of this scale. The support of his community is something Dave certainly does not take for granted.

The Next Steps on the Construction Site

The week ends with important progress inside the house, a solution for the delayed installations and the start of the pergola outside.

There is still plenty to do. The immediate goal, however, is clear: the missing pipes and installations need to be completed so that work on the floor build-up can begin and the next trades can start their work.

The house is changing step by step, even though the journey towards the finished result has become more complicated and more expensive than Dave originally expected.

That is exactly what makes this project what it is: it is not just about showing a house being built, but also about all the decisions, challenges and solutions required to turn an idea into a real home.